Buckinghamshire Council (26 017 901)
Category : Planning > Planning applications
Decision : Closed after initial enquiries
Decision date : 06 Oct 2026
The Ombudsman's final decision:
Summary: We cannot investigate this complaint about the Council’s refusal to withdraw an enforcement notice. This is because Mr and Mrs X have appealed against this decision to the planning inspectorate. We will not investigate their complaint about the delays in determining other planning applications. This is because it was reasonable for Mr and Mrs X to have used their right of appeal and the complaint is late.
The complaint
- Mr and Mrs X complain about the Council’s failure to determine planning applications relating to their property within a reasonable time over the past five years. They say that despite the Council upholding their complaints about the delays and refunding application fees, the application remains undetermined. Mr and Mrs X complain about failings in the Council’s complaints response and multiple procedural failings over the past five years.
- Mr and Mrs X also complain about the Council’s refusal to withdraw an enforcement notice after granting retrospective planning permission, which they say forced them to pursue an appeal. Mr and Mrs X want the Council to apologise, provide financial compensation, determine their planning application and implement procedural improvements.
The Ombudsman’s role and powers
- The Local Government Act 1974 sets out our powers but also imposes restrictions on what we can investigate.
- We cannot investigate a complaint if someone has appealed to a government minister. The Planning Inspector acts on behalf of a government minister. (Local Government Act 1974, section 26(6)(b), as amended)
- The law says we cannot normally investigate a complaint when someone can appeal to a government minister. However, we may decide to investigate if we consider it would be unreasonable to expect the person to appeal. (Local Government Act 1974, section 26(6)(b), as amended)
- The Planning Inspector acts on behalf of the responsible Government minister. The Inspector considers appeals about:
- delay – usually over eight weeks – by an authority in deciding an application for planning permission;
- a decision to refuse planning permission;
- conditions placed on planning permission;
- a planning enforcement notice.
- The courts have said that where someone has used their right of appeal, reference or review or remedy by way of proceedings in any court of law, the Ombudsman has no jurisdiction to investigate. (R v The Commissioner for Local Administration ex parte PH (1999) EHCA Civ 916).
- We cannot investigate late complaints unless we decide there are good reasons. Late complaints are when someone takes more than 12 months to complain to us about something a council has done. (Local Government Act 1974, sections 26B and 34D, as amended)
How I considered this complaint
- I considered information provided by the complainants.
- I considered the Ombudsman’s Assessment Code.
My assessment
- We cannot investigate Mr and Mrs X’s complaint about the Council’s refusal to withdraw the enforcement notice because they appealed to the Planning Inspectorate. Where a person has used a right of appeal, the restriction on our jurisdiction applies regardless of the outcome of the appeal.
- Mr and Mrs X say the Council’s actions amount to an ongoing pattern of fault, unreasonable conduct and procedural failure over several years. They refer to prolonged delays, repeated upheld complaints and poor communication. We will not investigate these matters because the complaint is late. I recognise Mr and Mrs X consider the 12-month restriction set out at paragraph 8 should not apply because the alleged fault is ongoing and concerns the same property. However, they were aware of the matters complained about more than 12 months before they complained to us in September 2026. If they remained dissatisfied with the Council’s actions, it would have been reasonable for them to complain to us sooner. Continued correspondence with the Council does not provide a good reason for the delay.
- Mr and Mrs X could have appealed to the Planning Inspectorate against the Council’s failure to determine the applications within the required period. This includes the most recent planning application that remains undetermined. It would have been reasonable for them to use that appeal right. In any event, this part of the complaint is late.
- We will not investigate the Council’s complaint handling separately. It is not a proportionate use of public resources to investigate complaint handling when we are not investigating the substantive matters complained about.
Final decision
- We cannot investigate part of Mr and Mrs X’s complaint because they have appealed to the planning inspectorate. For the remaining part of the complaint, it would have been reasonable for Mr and Mrs X to have used their right of appeal.
Investigator's decision on behalf of the Ombudsman