East Devon District Council (25 028 431)
Category : Planning > Planning applications
Decision : Closed after initial enquiries
Decision date : 05 Oct 2026
The Ombudsman's final decision:
Summary: We will not investigate Mr X’s and Ms Y’s complaint about the Council’s handling of a planning application. This is because there is not enough evidence of fault by the Council.
The complaint
- Mr X and Ms Y complain about the Council’s handling of a planning application. They say that it failed to properly consider its duties under the Equality Act 2010 (Equality Act). They also complain about the Council’s handling of their complaints.
The Ombudsman’s role and powers
- We investigate complaints about ‘maladministration’ and ‘service failure’, which we call ‘fault’. We must also consider whether any fault has had an adverse impact on the person making the complaint, which we call ‘injustice’. We provide a free service, but must use public money carefully. We do not start or continue an investigation if we decide:
- there is not enough evidence of fault to justify investigating, or
- any fault has not caused injustice to the person who complained, or
- we could not add to any previous investigation by the organisation, or
- further investigation would not lead to a different outcome. (Local Government Act 1974, section 24A(6), section 34(B))
- If there was no fault in how the organisation made its decision, we cannot question the outcome. (Local Government Act 1974, section 34(3), as amended)
How I considered this complaint
- I considered information provided by Mr X and Ms Y.
- I also considered the Ombudsman’s Assessment Code.
My assessment
- We are not an appeal body. This means we do not take a second look at a decision to decide if it was wrong. Instead, we look at the processes an organisation followed to make its decision. If we consider it followed those processes correctly, we cannot question whether the decision was right or wrong.
- We also cannot determine whether an organisation has breached the Equality Act. However, we can consider whether it failed to have proper regard to its duties under the Act.
- The officer’s report shows the Council considered Mr X’s and Ms Y’s objections and had regard to its duties under the Equality Act. It shows the applicant amended the plans in response to comments received and the Council was satisfied the applicant had made reasonable adjustments as required. It properly considered the ‘material’ planning issues and reached a decision it was entitled to reach. There is not enough evidence of fault in how the Council reached its decision and we therefore cannot question the outcome. The fact that Mr X and Ms Y believe the Council should have done more does not make the Council’s assessment inadequate or allow us to challenge it.
Further concerns
- Since the outcome of the planning application, Mr X and Ms Y have raised further concerns about the development. As a publicly funded body we must be careful how we use our resources. This means we cannot always respond to complaints in the level of detail people might want. We have limited resources and must investigate complaints in a proportionate manner, focusing on general themes and issues, rather than providing a response to every individual issue raised in a complaint. For this reason, I have not referred to every element of information that Mr X and Ms Y have raised but I have not ignored its significance.
- I have reviewed the additional concerns that Mr X and Mrs Y have raised. I do not consider they demonstrate:
- fault in the Council’s assessment of the planning application; or
- the development was not constructed in accordance with the approved plans.
Therefore, the Council was entitled not to take further action in the circumstances.
- As the development was constructed in accordance with the approved plans, and there is not enough evidence of fault in how the Council assessed the application, then any outstanding concerns Mr X and Ms Y have raised are a private matter between them and the landowner.
Complaint handling
- Mr X and Ms Y also complain the Council did not properly address their concerns. I have reviewed the complaints and the Council’s complaint responses. I consider the Council has appropriately addressed their concerns and provided an adequate response. Further investigation by us would not lead to a different outcome or add to the Council’s investigation of the matter.
Final decision
- We will not investigate Mr X’s and Ms Y’s complaint because there is not enough evidence of fault in the Council’s handling of the planning application and because further investigation of the complaint handling would not lead to a different outcome.
Investigator's decision on behalf of the Ombudsman