Summary: Mr X complains on behalf of Mr Y and Ms W that the Council made a flawed decision when it approved plans for development close to their home. He says the Council did not properly consider the impact on light and wrongly approved the development despite it failing the relevant tests. We find the Council made a decision which was not impacted by fault. The errors in a daylight study had no bearing on the decision made, and the other issues raised by Mr X are matters of professional judgement which, in the absence of procedural fault, the Ombudsman cannot question.

The complaint

  1. Mr X complains on behalf of Mr Y and Ms Z about how the Council dealt with an application for a development near their home. Mr X says the Council has not considered the application in line with planning policy and failed to properly address the impact on Mr Y and Ms Z’s home.
  2. Mr X says Mr Y and Ms Z have suffered injustice in the form of lost amenity.

Back to top

The Ombudsman’s role and powers

  1. We investigate complaints of injustice caused by ‘maladministration’ and ‘service failure’. I have used the word ‘fault’ to refer to these. We cannot question whether a council’s decision is right or wrong simply because the complainant disagrees with it. We must consider whether there was fault in the way the decision was reached. (Local Government Act 1974, section 34(3), as amended)
  2. If we are satisfied with a council’s actions or proposed actions, we can complete our investigation and issue a decision statement. (Local Government Act 1974, section 30(1B) and 34H(i), as amended)

Back to top

How I considered this complaint

  1. During my investigation I discussed the complaint with Mr X and considered the information he submitted.
  2. I consulted the plans in question, the daylight studies, relevant planning policies and the webcast of the Council’s Planning Committee meetings.
  3. I made enquiries of the Council and considered its response.
  4. I issued a draft decision inviting comments from Mr X and the Council. I considered any comments received before making a final decision.

Back to top

What I found

Key background information

  1. The Council received a planning application in 2019 to demolish an existing house and build a three-storey block to accommodate nine self-contained flats near Mr Y and Ms Z’s home. Mr X objected to the proposal on behalf of affected residents. The application was referred to the Council’s Planning Committee for determination and permission was granted subject to conditions.
  2. Mr X has complained about the Council’s decision to grant planning permission. He says it has not properly considered the impact on Mr Y and Ms Z’s home, particularly in relation to loss of light. He also argues the application will be overbearing, out of character with the area and not in line with the London Plan.
  3. Dissatisfied with the Council’s response to his complaint, Mr X approached the Ombudsman for an impartial review. At the Assessment stage of our process, we decided that Mr X’s complaint was one that we should not investigate because it is unlikely that we would find fault. We issued a draft decision on that basis.
  4. Mr X responded to the draft decision, outlining his objections to our findings. After reviewing his comments, we decided to pass Mr X’s case for investigation to look at how the Council considered his points about loss of light and the 45-degree rule. I have investigated these points, and my findings are explained in the section below.
  5. However, we did not consider there was fault in Mr X’s complaint about compliance with the Local Plan or the style and character of the development, because the concerns he raised were a matter of professional judgement. I maintain that view for the reasons explained below.

Mr X’s complaints

Compliance with the Local Plan

  1. The Council says the development which Mr X complains about ‘marginally’ exceeds the habitable rooms per hectare density outlined in policy 3.4 of the London Plan. Mr X disagrees with the Council’s method of calculation and says the development is significantly above the London Plan requirements.
  2. The London Plan is a material planning consideration. But the policy says it is not appropriate to apply the density matrix mechanistically; it is used as a starting guide to development, and some policy considerations may not align with others.
  3. Policies provide guidance; they do not bind the Council to a particular decision, although if the Council is to depart from policy it should give reasons. The Council’s role was to weigh up the issues against other material considerations and decide if the proposal was acceptable. The case officer’s report details why, in their professional view, the proposed density levels are acceptable. I understand Mr X does not agree with the calculations used, and the Council’s decision to grant planning permission. However, the officer used their professional judgement and properly considered the application, taking into account the density matrix in the London Plan, before granting permission. I find no evidence of fault in this part of the decision-making process.

Loss of amenity

  1. Mr X says the development is out of character with the area, is overbearing and will have a significant impact on Mr Y and Ms Z’s home. I have considered the case officer’s report to establish how the Council assessed the impact on residential amenity before deciding the proposal was acceptable.
  2. The report says the development protects the street scene, complies with the policy recommendations in relation to residential amenity and resembles a large, detached house which preserves the character of the area and neighbouring properties.
  3. I understand Mr X does not agree with this assessment, but the case officer was entitled to use their professional judgement about the style and character of the development. The Ombudsman cannot question this judgement unless there is evidence to show it was flawed. I have found no such evidence.

Loss of light and compliance with the 45-degree guidance

  1. The ‘45-degree’ Building Research Establishment (BRE) guidance forms part of many council planning processes when assessing the impact of new developments on existing developments. It is a test officers may conduct using the plans and elevation drawings supplied by the planning applicant.
  2. If a proposed development does not comply with the 45-degree test, it may be less likely to receive planning permission. This is because the 45-degree tests are indicators of planning harm to the existing property, particularly the decrease in daylight received by the affected windows.
  3. However, non-compliance with the test does not mean officers must refuse an application. The test may be one part of the planning officer’s assessment of levels of planning harm caused by a proposed development. Each application should be judged on its own facts and circumstances, and officers retain their ability to use their professional judgement.
  4. Paragraph 2.9.3 of the Council’s ‘Suburban Design Guide’ says: “Where there is concern that the orientation of the proposal and proximity to neighbouring buildings will limit access to natural light within the proposed and/or neighbouring dwellings, proposals will be required to provide a daylight and sunlight analysis study”.
  5. Due to the potential impact on the light received into Mr Y and Ms Z’s home, the developer arranged two light analysis studies. The first one in March 2019 concluded:
    • The west elevation of Mr Y and Ms W’s home may experience an ‘adverse impact in terms of daylight and sunlight’. The western side of the house has three relevant windows. Two of those windows serve bathrooms and are ‘non-habitable rooms’.
    • The results show the effect on the side windows meet the minimum requirements set by the BRE guidelines and experience a ‘negligible impact in terms of daylight and sunlight’.
    • The proposed development meets the recommended levels and is considered acceptable in daylight terms.
  6. The planning officer’s report concluded, “There would be a small increase in height and a significant increase in depth from the current building but the 45-degree BRE test for loss of light to the rear elevation windows would not be breached. The rear garden to [address removed] faces due north and whilst there are side windows facing towards the application property (ground floor lighting a living room and the two first floor windows lighting bedrooms) all these windows appear (after reviewing historic floor plans) to be secondary in nature. The applicant has also submitted an External Daylight Study which finds satisfactory outcomes for these windows in accordance with BRE guidelines”.
  7. The officer recommended approval of the application because they considered the proposed development was “acceptable within the area” and is of “… an acceptable standard”.
  8. A councillor ‘called in’ the planning application and it was considered by the Council’s Planning Committee. I have viewed the webcast recording for the meeting, and the following key points were discussed:
    • Planning officer said the 45-degree line was not exceeded;
    • The density matrix is exceeded, but no harm caused. Housing targets have changed since the matrix was produced in 2006;
    • Mr Y spoke in objection to say the proposal was overdevelopment, fails the 45-degree test, and his north facing garden will be significantly impacted by lost light. Mr Y also said there would be overlooking, loss of privacy, and congestion from parking.
  9. Committee members decided, with a vote of six against three, that the application should be deferred for design amendments to overcome the issues raised.
  10. The developers submitted amended plans. The new plans increased the proposed roof height, and so the developers commissioned a second light survey in September 2019, which concluded:
    • There are five relevant windows in Mr Y and Ms Z’s home that may be affected by the proposed development.
    • The results show the effect on the side windows meet the minimum requirements set by the BRE guidelines and experience a ‘negligible impact in terms of daylight and sunlight’
  11. The survey did not confirm which of the five windows mentioned serve habitable rooms.
  12. The planning officer wrote a further report in response to the amended plans. It acknowledged the breach of the 45-degree guidance, “As the height of the building has been increased by 1.05m the applicant has submitted a revised Daylight and Sunlight Study which assesses the impact upon [address removed]. The development does marginally break the vertical 45 degree line, however the Daylight and Sunlight Study demonstrates that the effect of the proposal upon the side windows of this neighbour would be negligible and accords with BRE guidelines. A horizontal 45 degree line without obstruction is maintained from the closest rear window of this neighbour to the rear of the proposed building.”
  13. The Planning Committee considered the amended plans. The key points discussed at the meeting were:
    • The planning officer spoke to give their view that harm is not demonstrated. Car parking standards are met. The 45-degree guide is breached, but the proposal meets other planning requirements.
    • Mr Y reiterated the proposal did not meet the 45-degree guidance and should therefore be refused. He said the second light survey is incomplete. Critical windows are not included, and the study does not consider that his windows are small due to the nature of his house. The report is also silent on the loss of natural light to his rear garden.
    • Councillors discussed the impact on Mr Y and Ms W. Some felt there would be impact, but the BRE guidance is not absolute. The amended plans included removal of a garage which may improve light. Mr Y’s garden is not overshadowed for most of the day due to its orientation.
    • Some councillors felt the scheme is dominant in its size and there is a cumulative impact resulting from more than one policy breach.
  14. After discussing the merits of the scheme, Committee members voted six, versus three, in favour of approval.
  15. Mr X disagrees with the Council’s decision. In response to the Ombudsman’s first draft decision, Mr X reiterated his complaint was about the Council’s failure to recognise the true impact on Mr Y and Mrs Z. He said the Council’s decision was flawed because:
    • The light survey relates only to windows and internal rooms, not outdoor spaces. The officer’s analysis regarding outdoor space was based on guess work only.
    • The light survey contains errors and omissions. The first survey excluded some windows and confused habitable rooms with non-habitable rooms. The Council ignored Mr X’s requests for these points to be considered.
    • The development breaches the 45-degree test.
  16. When investigating this part of Mr X’s complaint, I have considered a floor plan of Mr Y and Ms Z’s home, which shows the location of all windows and doors. I have compared this with the daylight studies, external photographs taken by the Council and internal photographs taken by Mr Y.
  17. Mr X says the first daylight study wrongly concluded that windows five and six served a non-habitable room (bathroom), whereas they in fact serve a bedroom. In my view, the contents of the first daylight study are irrelevant because the findings were superseded by the second study. The Planning Committee made its decision based on the second study and so this is the one which needs to be considered.
  18. The second study did not stipulate whether affected windows served habitable rooms or not. It merely assessed the percentage of light lost. Irrespective of whether the rooms are habitable or not, the study found the impact to be negligible.
  19. Mr X is correct to point out the study omitted a window, which he refers to as window six. As part of my investigation, I asked Mr X to clarify the location of all affected windows and to confirm whether they are secondary in nature. He explained that one bedroom is served by two windows (windows five and six). Furthermore, window four serves another bedroom which is also dual aspect, as it benefits from a second window.
  20. The planning officer and Committee made their decision not only on the findings of the survey, but in conjunction with the floor plans of Mr Y and Ms W’s home and the officer’s photographs. The officer noted in their first report that the affected windows served habitable rooms. Mr Y also made this clear when he spoke at the Committee meeting. I am therefore satisfied the Committee had knowledge of the facts and were able to make an informed decision.
  21. I find the errors in the first daylight study had no impact on the Council’s decision. Furthermore, in my view, the omission of window six from the second study is unlikely to have had any bearing on the decision. This is because the Council was satisfied the bedroom in question suffered only a ‘negligible’ impact. It therefore follows that the impact on overall light into the bedroom would be even less, had all parties known the room is served by two windows.
  22. I am also satisfied, based on the information seen, that the Committee was made aware of the impact on Mr Y and Ms Z’s garden. Although not included in the study, Mr Y made this point clear when he spoke in person at both Committee meetings. The Committee was therefore able to make an informed decision after considering Mr Y’s comments, as well as the location and orientation of his garden in relation to the development, as shown on the plans which were available to them.
  23. In my view, the officer and Committee made a decision which was not influenced by procedural fault. Although the original study wrongly designated some windows, the officer made clear in their report that the rooms were habitable. This was also discussed at Committee, and the second study again reiterated a negligible impact on all windows.
  24. For the reasons explained above, I do not uphold the complaint.

Back to top

Final decision

  1. I have completed my investigation with a finding of no fault for the reasons explained in this statement.

Back to top

Investigator's decision on behalf of the Ombudsman

Print this page

LGO logogram

Review your privacy settings

Required cookies

These cookies enable the website to function properly. You can only disable these by changing your browser preferences, but this will affect how the website performs.

View required cookies

Analytical cookies

Google Analytics cookies help us improve the performance of the website by understanding how visitors use the site.
We recommend you set these 'ON'.

View analytical cookies

In using Google Analytics, we do not collect or store personal information that could identify you (for example your name or address). We do not allow Google to use or share our analytics data. Google has developed a tool to help you opt out of Google Analytics cookies.

Privacy settings