Summary: We will not investigate this complaint about how the Council handled a planning enforcement complaint. This is because there is insufficient evidence of fault by the Council.

The complaint

  1. Mr X has complained about how the Council dealt with possible breaches of planning control. Mr X says the Council was not clear about what breaches he could report to its enforcement team. He says a Council Officer accused him of making malicious reports which caused him stress. He wants the Council to apologise and remove the Officer from the case.

Back to top

The Ombudsman’s role and powers

  1. We investigate complaints about ‘maladministration’ and ‘service failure’, which we call ‘fault’. We must also consider whether any fault has had an adverse impact on the person making the complaint, which we call ‘injustice’. We provide a free service, but must use public money carefully. We do not start or continue an investigation if we decide:
  • there is not enough evidence of fault to justify investigating, or
  • any injustice is not significant enough to justify our involvement, (Local Government Act 1974, section 24A(6), section 34(B))
  1. We consider whether there was fault in the way an organisation made its decision. If there was no fault in how the organisation made its decision, we cannot question the outcome. (Local Government Act 1974, section 34(3), as amended).

Back to top

How I considered this complaint

  1. I considered information provided by Mr X and the Council.
  2. I considered the Ombudsman’s Assessment Code.

Back to top

My assessment

  1. The Council granted planning permission for a development near Mr X’s home. Mr X reported several concerns to the Council about breaches of planning permission and the behaviour of builders. Other residents complained to the Council about similar issues.
  1. Councils can take enforcement action if they find a breach of planning rules. This is discretionary; it is up to the council whether to take action and what action to take.
  1. We will not investigate this complaint because there is insufficient evidence of fault by the Council. I am satisfied the Council properly considered the alleged breaches reported by Mr X. It conducted site visits and assessed the land levels and drainage. It told Mr X the development was ongoing so the drainage was not finalised. It also said some of the work carried out was permitted development and therefore did not need planning permission.
  2. It concluded although there was a rise in the land level at a section of the site, it was not expedient to consider enforcement action. This is a professional judgement the Council was entitled to make and councils do not need to take formal action just because there has been a breach.
  3. Mr X reported concerns about the conduct and behaviour of the builders on site. Councils often impose construction management planning conditions on approvals for major developments. Typically, these conditions are aimed at reducing the impact and disruption caused by:
  • long working hours on construction sites;
  • nuisance from noise, dust, smoke and vibration; and
  • traffic from construction vehicles.
  1. While construction management conditions may help lessen the harmful impact of major development, they cannot ensure it is avoided entirely. To justify formal enforcement action for this type of condition, councils usually need evidence of persistent breach of planning controls, that causes demonstrable harm to the public. In this case, the Council conducted site visits and investigated Mr X’s concerns. It decided it was not expedient to take enforcement action.
  2. Mr X said the Council claimed his reports were malicious within the email chain that was shared with other people. However, the Council officer did not say Mr X himself was malicious.
  3. It also explained to Mr X why it would not remove the Officer from the case as his point of contact. The Council explained why it would not remove them from the site and there is insufficient evidence of fault in the Council’s decision for me to question the outcome.
  4. Mr X also complained about the Council’s complaint handling. However, where the Ombudsman has decided not to investigate the substantive issues complained about, we will not usually use public resources to consider more minor matters such as complaint handling.

Back to top

Final decision

  1. We will not investigate Mr X’s complaint because there is insufficient evidence of fault by the Council.

Back to top

Investigator's decision on behalf of the Ombudsman

Print this page

LGO logogram

Review your privacy settings

Required cookies

These cookies enable the website to function properly. You can only disable these by changing your browser preferences, but this will affect how the website performs.

View required cookies

Analytical cookies

Google Analytics cookies help us improve the performance of the website by understanding how visitors use the site.
We recommend you set these 'ON'.

View analytical cookies

In using Google Analytics, we do not collect or store personal information that could identify you (for example your name or address). We do not allow Google to use or share our analytics data. Google has developed a tool to help you opt out of Google Analytics cookies.

Privacy settings