Bournemouth, Christchurch and Poole Council (25 014 824)
The Ombudsman's final decision:
Summary: We have found fault with the Council in how it communicated its planning enforcement decision to Mr X. This caused him avoidable uncertainty and frustration. The Council has agreed to apologise to Mr X.
The complaint
- Mr X complains the Council failed to take adequate planning enforcement against a developer. He said the developer failed to comply with planning conditions to complete road works related to a development near Mr X’s home. He said this has led to safety risks, anti-social behaviour, fly-tipping and general stress and confusion.
The Ombudsman’s role and powers
- We investigate complaints of injustice caused by ‘maladministration’ and ‘service failure’. I have used the word fault to refer to these. We consider whether there was fault in the way an organisation made its decision. If there was no fault in how the organisation made its decision, we cannot question the outcome. (Local Government Act 1974, section 34(3), as amended)
- We cannot investigate late complaints unless we decide there are good reasons. Late complaints are when someone takes more than 12 months to complain to us about something a council has done. (Local Government Act 1974, sections 26B and 34D, as amended)
- If we are satisfied with an organisation’s actions or proposed actions, we can complete our investigation and issue a decision statement. (Local Government Act 1974, section 30(1B) and 34H(1), as amended)
What I have and have not investigated
- Mr X brought his complaint to the Ombudsman in October 2025. The complaint relates to matters that took place from 2022 onwards. This part of the complaint is late and section 26b applies. I have not exercised my discretion to investigate back earlier than October 2024 (12 months before Mr X brought his complaint to us) as I see no reason why Mr X did not complain sooner.
How I considered this complaint
- I considered evidence provided by Mr X and the Council as well as relevant law, policy and guidance.
- Mr X and the Council had an opportunity to comment on my draft decision. I considered any comments received before making a final decision.
What I found
Law and guidance
- Councils can take enforcement action if they find a breach of planning rules. However, councils should not take enforcement action just because there has been a breach of planning control.
- Planning enforcement is discretionary and formal action should happen only when it would be a proportionate response to the breach. When deciding whether to enforce, councils should consider the likely impact of harm to the public and whether they might grant approval if they were to receive an application for the development or use.
- As planning enforcement action is discretionary, councils may decide to take informal action or not to act at all. Informal action might include negotiating improvements, seeking an assurance or undertaking, or requesting submission of a planning application so they can formally consider the issues.
- Government guidance says: “Effective enforcement is important as a means of maintaining public confidence in the planning system. Enforcement action is discretionary, and local planning authorities should act proportionately in responding to suspected breaches of planning control.” (National Planning Policy Framework December 2024, paragraph 60)
What happened
Background
- Mr X lives in a cul-de-sac near to a new residential development. The planning permission required the completion of roadworks and highway adoption before the occupation of the residential building. Mr X said the new residents occupied the building in 2022 before the road was finished. He said this led to illegal parking in the cul-de-sac, fly tipping, antisocial behaviour and safety risks due to the road being blocked. Mr X reported his concerns to the Council.
- The Council carried out an enforcement investigation but closed the case before taking any action.
Complaint about planning enforcement
- In July 2025, Mr X complained the Council failed to enforce a planning condition requiring the developer to complete the road before occupation. The Council said it was liaising with the developer to ensure it completed the works but had no influence over the timescale for the works to take place. Mr X escalated his complaint stating that the developer had breached planning control as the works should have been complete before the occupation of the building.
- The Council accepted that it was incorrect to say it had no influence over the timescale. It acknowledged that the developer had breached planning control by allowing the occupation of the building before it had completed all the road works. It said that it was not expedient to take formal enforcement action due to the potential costly legal expenses and the limited impact the breach had on the wider public.
- The Council said that it would continue to monitor the site and expediate the works to and adoption of the road. It also said it would escalate the topic of enforcement of highway related conditions with the planning department, specifically pre-occupation conditions attached to new developments.
Update
- During our investigation, the developer has cleared the building compound from the road, but the adoption of the highway remains outstanding.
My findings
- The Ombudsman is not an appeal body. This means we do not take a second look at a decision to decide if it was wrong. Instead, we look at the processes the Council followed to make its decision. If we consider it followed those processes correctly, we cannot question whether the decision was right or wrong, regardless of whether you disagree with the decision the Council made.
- I have considered the steps the Council took to consider the alleged breach of planning control, and the information it took account of when deciding not to take enforcement action. I have found no fault in how it took the decision and I therefore cannot question whether that decision was right or wrong.
- I have however found fault with how the Council communicated its enforcement decision to Mr X. It was not until its response to Mr X’s complaint, the Council confirmed the developer had breached planning control by allowing the occupation of the property before the completion of the road works. The Council should have communicated this sooner to Mr X that although a breach had occurred, it did not consider it expedient to take formal enforcement action. Instead, the issue dragged on for 4 years.
- The poor communication caused Mr X the injustice of uncertainty and frustration. The Council has agreed to apologise to Mr X. The Council has raised the issue of pre-occupation highway conditions with planning which should ensure that similar problems do not arise in the future.
Agreed action
- Within 4 weeks of my decision, the Council will:
- Apologise to Mr X for how it communicated its planning enforcement decision to him.
Decision
- I find fault causing injustice. The Council has agreed to remedy injustice.
Investigator's decision on behalf of the Ombudsman