The Ombudsman's final decision:

Summary: We will not investigate this complaint about the way the Council dealt with a planning application and a report of a breach of planning control. We have not seen enough evidence of fault to justify an investigation.

The complaint

  1. Mrs X complains about the Council’s decision to grant planning permission for her neighbour to extend their property. And its’ decision not to take enforcement action against a breach of planning control.
  2. She wants the extension demolished and the application reconsidered.

Back to top

The Ombudsman’s role and powers

  1. We investigate complaints about ‘maladministration’ and ‘service failure’, which we call ‘fault’. We must also consider whether any fault has had an adverse impact on the person making the complaint, which we call ‘injustice’. We provide a free service but must use public money carefully. We do not start or continue an investigation if we decide there is not enough evidence of fault to justify investigating. (Local Government Act 1974, section 24A(6), section 34(B))

Back to top

How I considered this complaint

  1. I considered information provided by Mrs X and the Council.
  2. I considered the Ombudsman’s Assessment Code.

Back to top

My assessment

  1. In 2023, the Council received a planning application from Mrs X’s neighbour to extend their property. Mrs X and others objected to the application. However, the planning officer’s report shows the Council considered the impact of the application on the neighbouring properties and outlined the relevant national and local planning policies. The officer explained why they considered the proposal was acceptable and the Council approved the application.
  2. In 2024, following reports of breaches of planning control, the Council received an application for what had been built.
  3. Again, the Council received objections and a summary of these, including those made by Mrs X, are included in the planning officer’s report.
  4. The officer recommended the application for approval as they considered the changes to the extension would not affect the neighbours’ amenity, highway safety or the general area.
  5. The Council considered the application and agreed with the planning officers’ recommendation. They approved the application.
  6. Mrs X told the Council the extension is higher than shown on the approved plans.
  7. The Council confirms a planning enforcement officer has visited the property. They are satisfied there is no evidence the extension is too high. The cladding to the dormer window is a minor breach. However, they consider this does not cause enough planning harm to warrant action.
  8. We are not an appeal body. Our role is not to ask whether an organisation could have done things better, or whether we agree or disagree with what it did. Instead, we look at whether there was fault in how it made its decisions. If we decide there was no fault in how it did so, we cannot ask whether it should have made a particular decision or say it should have reached a different outcome.
  9. The role of the Council as local planning authority is to reach a judgement about whether a development is acceptable after consideration of local and national planning policies; comments from statutory consultees and objections/representations from people affected by the decision. The evidence strongly suggests that this is what has happened in this case and therefore it is unlikely we would find fault in the way the Council dealt with the planning applications.
  10. Also, the Council has confirmed there is no breach of planning control except for the cladding on the dormer window. It has exercised its discretion not to take enforcement action against this minor breach of planning control. This is a decision the Council is entitled to make.

Back to top

Final Decision

  1. We will not investigate Mrs X’s complaint because there is not enough evidence of fault in the way the Council considered the planning applications and reports of breaches of planning control.

Back to top

Investigator's decision on behalf of the Ombudsman

Print this page

LGO logogram

Review your privacy settings

Required cookies

These cookies enable the website to function properly. You can only disable these by changing your browser preferences, but this will affect how the website performs.

View required cookies

Analytical cookies

Google Analytics cookies help us improve the performance of the website by understanding how visitors use the site.
We recommend you set these 'ON'.

View analytical cookies

In using Google Analytics, we do not collect or store personal information that could identify you (for example your name or address). We do not allow Google to use or share our analytics data. Google has developed a tool to help you opt out of Google Analytics cookies.

Privacy settings