Summary: We will not investigate this complaint about the Council’s failure to ensure Mr X’s new home was built according to approved plans. We do not consider an investigation to be good use of our resources as we cannot achieve the outcome Mr X is seeking.
The complaint
- Mr X complains the Council issued a completion certificate for his new home without checking the building was built according to the approved plans.
- He wants the Council to either:
- Carry out remedial work to ensure the property complies with the original approved plans; or
- Compensate him for the cost to have the remedial work carried out himself.
The Ombudsman’s role and powers
- We investigate complaints about ‘maladministration’ and ‘service failure’, which we call ‘fault’. We must also consider whether any fault has had an adverse impact on the person making the complaint, which we call ‘injustice’. We provide a free service but must use public money carefully. We do not start or continue an investigation if we decide we cannot achieve the outcome someone wants.
(Local Government Act 1974, section 24A(6), as amended, section 34(B))
How I considered this complaint
- I considered information provided by the complainant.
- I considered the Ombudsman’s Assessment Code.
My assessment
- Mr X says the Council failed to ensure his new home was built according to the approved plans because floor joists are missing. The building control record I have seen states: “floor joists - existing and new – all satisfactory.” The Council issued a completion certificate for the property.
- However, responsibility for building work and compliance with the building regulations rests with building owners and builders.
- When carrying out their building control functions, councils will normally visit at various stages, but they are not required to do so and will not be present for most of the project. Councils are not expected to act as a site manager or ‘clerk of works’.
- A Council may inspect work or issue a completion certificate, but this is not a guarantee that all works meet with Building Regulations. The Council’s role is to maintain building standards for the public in general, rather than to protect the private interests of individuals.
- The courts have held that local authorities are not responsible for the costs of putting right defective building work which does not meet the building regulations.
- This means that, even if an investigation found the Council was at fault, we would not ask the Council to pay to correct the defect when the courts have decided local authorities are not liable.
Final decision
- We will not investigate Mr X’s complaint because an investigation would not be a good use of our limited resources as we cannot achieve the outcome he is seeking.
Investigator's decision on behalf of the Ombudsman