Devon County Council (25 016 376)

Category : Education > Special educational needs

Decision : Upheld

Decision date : 13 Oct 2026

The Ombudsman's final decision:

Summary: We found the Council at fault for delays in issuing Mrs X’s child’s Education, Health and Care Plan, and delays in paying a personal budget. The Council’s actions caused Mrs X financial hardship and caused her child to miss out on education. The Council has agreed to apologise and make a payment to recognise the injustice caused to Mrs X and her child. It has also agreed to make changes to its service to prevent the same faults from happening again.

The complaint

  1. Mrs X complained the Council delayed amending her child, Y’s, Education, Health and Care Plan. She said this delayed the Council agreeing and paying Y’s personal budget, so Mrs X had to pay for some of Y’s support herself while she waited. She said this caused financial hardship and Y missed out on education.
  2. Mrs X also complained the Council’s communication with her about these matters was poor. She said this added to her distress.

Back to top

The Ombudsman’s role and powers

  1. We investigate complaints about ‘maladministration’ and ‘service failure’. In this statement, I have used the word fault to refer to these. We must also consider whether any fault has had an adverse impact on the person making the complaint. I refer to this as ‘injustice’. If there has been fault which has caused significant injustice, or that could cause injustice to others in the future we may recommend a remedy. (Local Government Act 1974, sections 26(1) and 26A(1), as amended)
  2. When considering complaints we make findings based on the balance of probabilities. This means that we look at the available relevant evidence and decide what was more likely to have happened.
  3. If we are satisfied with an organisation’s actions or proposed actions, we can complete our investigation and issue a decision statement. (Local Government Act 1974, section 30(1B) and 34H(1), as amended)

Back to top

How I considered this complaint

  1. I considered evidence provided by Mrs X and the Council as well as relevant law, policy and guidance.
  2. Mrs X and the Council had an opportunity to comment on my draft decision. I considered any comments before making a final decision.
  3. Under our information sharing agreement, we will share this decision with the Office for Standards in Education, Children’s Services and Skills (Ofsted).

Back to top

What I found

Relevant law and guidance

Education, Health and Care Plans

  1. A child or young person with Special Educational Needs (SEN) may have an Education, Health and Care (EHC) Plan. This document sets out the child’s needs and what arrangements should be made to meet them. The EHC Plan is set out in sections.
  2. The council has a duty to make sure the child or young person receives the special educational provision set out in section F of an EHC Plan (Children and Families Act 2014, section 42).

Reviews of EHC Plans

  1. The council must arrange for the EHC Plan to be reviewed at least once a year to make sure it is up to date. The council must complete the review within 12 months of the first EHC Plan and within 12 months of any later reviews. The annual review begins with consulting the child’s parents or the young person and the educational placement. A review meeting must then take place. Following the review meeting the council must issue a decision to either amend, maintain or cease to maintain the EHC Plan. This must happen within four weeks of the meeting. (Section 20(10) Special Educational Needs and Disability Regulations 2014 and SEN Code paragraph 9.176) 
  2. Where the council proposes to amend an EHC Plan, the law says it must send the child’s parent or the young person a copy of the existing (non-amended) Plan and an accompanying notice providing details of the proposed amendments, including copies of any evidence to support the proposed changes. (Section 22(2) Special Educational Needs and Disability Regulations 2014 and SEN Code paragraph 9.194). Case law sets out this should happen within four weeks of the date of the review meeting. Case law also found councils must issue the amended final EHC Plan within a further eight weeks.

Education Otherwise Than At School

  1. If school or college is not appropriate for the child or young person with an EHC Plan (for either all or part of their education), the council can arrange for any special educational provision which the child or young person requires to be delivered somewhere other than in a school, college or early years setting. This is known as ‘education otherwise than at school’ (EOTAS). (Children and Families Act 2014, section 61)

Personal budgets

  1. A personal budget is the amount of money the council has identified it needs to pay to secure the provision in a child or young person’s EHC Plan. One way that councils can deliver a personal budget is through direct payments. These are cash payments made to the child’s parent or the young person so they can commission the provision in the EHC Plan themselves.

What happened

  1. Y had an EHC Plan. The Council agreed to provide Y with EOTAS and provide direct payments to Mrs X to pay for some EOTAS, but this was not written into Y’s EHC Plan.
  2. In May 2025 the Council held a meeting to review Y’s EHC Plan. The following month, it told Mrs X it would amend Y’s EHC Plan after the review.
  3. In September 2025 Mrs X complained to the Council because it had not yet sent Y’s amended final EHC Plan as it should have done. She said this meant the Council had failed to secure Y’s educational provision on time. She also complained the Council’s communication with her was poor.
  4. The Council sent Y’s amended final EHC Plan in October 2025. The EHC Plan described Y’s EOTAS package, which said they would get 25 hours of tuition and therapy each week, for 38 weeks of the year.
  5. The Council then responded to Mrs X’s complaint. It apologised for the delays with Y’s EHC Plan and EOTAS package. It said it was finalising Y’s EOTAS package.
  6. Mrs X then complained to us. She said the Council had failed to secure Y’s EOTAS package or pay for it, which meant she was having to pay for it herself. She said, even with her paying for some, Y was not getting everything they were entitled to.
  7. The Council started paying for some of Y’s educational provision in October 2025.
  8. In November 2025 the Council paid Mrs X some money to repay what she had spent on Y’s education since September 2025. It also started making direct payments for part of Y’s educational provision.
  9. Mrs X told us the Council had still not remedied the provision Y had missed, even though it had started paying for Y’s education.
  10. Mrs X also complained that Y’s EOTAS package was one hour less than it should be every week, so Y was not getting all the educational provision they should have been. She said she had started paying for one hour a week of educational provision for Y, and the Council had not yet repaid this.
  11. In June 2026 the Council secured Y’s full EOTAS package through a mix of paying for some support itself and paying Mrs X direct payments for the rest.

Analysis

Delays in amending the EHC Plan

  1. The law says if a council is going to amend an EHC Plan after a review, it should send the final EHC Plan within 12 weeks of the review meeting.
  2. In Y’s case, the Council sent their amended final EHC Plan about 10 weeks late. This was fault.
  3. This fault caused Y injustice, because it caused them to miss out on educational provision while waiting for their amended final EHC Plan. The fault also caused Mrs X uncertainty and frustration because she was paying for Y’s provision and didn’t know when the Council would decide Y’s EOTAS package.

Y’s special educational provision

  1. Y’s amended final EHC Plan stated their EOTAS package would be 25 hours a week of tuition or therapy, for 38 weeks of the year. On balance, it is likely the Council intended for Y’s EOTAS package to start at the beginning of September 2025 and end in July 2026, so I have considered Y’s education for that period.
  2. During September 2025, Y received 15 hours per week of educational provision, paid for by Mrs X. For this period, Y missed out on 10 hours per week of provision.
  3. From October 2025 until February 2026, Y received 24 hours per week of educational provision, paid for by the Council. This was a loss of 1 hour per week of provision.
  4. Therefore, the Council did not ensure Y received their full EOTAS package between September 2025 and February 2026. This was fault by the Council which caused Y to miss out on educational provision.
  5. In February 2026 Mrs X started paying for one hour a week of provision to make sure Y received their full EOTAS package. Therefore, any injustice to Y ended in February 2026.
  6. However, this caused Mrs X to experience her own injustice. She paid for some of Y’s EOTAS package, which she should not have had to do. It was the Council’s responsibility to pay for Y’s full EOTAS package.

Communication

  1. Mrs X complained to the Council about its poor communication. In its complaint response, the Council did not directly address this issue.
  2. Having reviewed the relevant available evidence, it is more likely, on balance, the Council was not always responsive to Mrs X. This was fault.
  3. This fault caused Mrs X injustice because it added to her uncertainty and frustration.

Financial remedies

  1. We use our guidance on remedies to help us decide suitable remedies for injustice caused by a council’s fault.

Delays in amending the EHC Plan and poor communication

  1. Where a council’s fault has caused someone avoidable distress, we can recommend a symbolic payment to acknowledge this. In Y’s case, £200 is appropriate to recognise the uncertainty and frustration caused to Mrs X by the Council delaying amending the EHC Plan and its poor communication.

Failure to secure Y’s special educational provision

  1. If a child has missed out on special educational provision because of a council’s fault, we will normally recommend a symbolic payment. In Y’s case, the following symbolic payments are fitting:
  • for September 2025, a total of £400 to recognise the loss of 10 hours a week of educational provision for the month; and,
  • from October 2025 to February 2026, a total of £400 to recognise the loss of 1 hour a week of educational provision for the period.
  1. Our guidance also explains that where, because of a council’s fault, someone had to pay for a service privately they should not have had to, we can consider reimbursing their costs.
  2. The Council will pay back Mrs X’s costs for one hour a week of educational provision between February 2026 and June 2026. It was reasonable for her to pay this, as she was making sure Y received their whole EOTAS package as outlined in their EHC Plan.

Service improvements

  1. Where we find fault by an organisation, we can recommend changes to improve how the organisation delivers its services to prevent the same issue happening to others.
  2. The Council said it delayed amending Y’s EHC Plan because it was finalising their EOTAS package.
  3. The statutory deadlines to amend an EHC Plan following a review are the same even when a parent or young person asks for EOTAS during the review.
  4. The Council has agreed to review its services to ensure that if a parent or young person asks for an EOTAS package during an EHC Plan review, it does not delay the finalising of an EHC Plan. We will monitor the effectiveness of the Council’s actions through our casework.

Back to top

Agreed action

  1. Within four weeks of our final decision, the Council will:
      1. apologise to Mrs X for the injustice caused to her and Y by the faults identified during this investigation. This apology should be in line with our guidance for making an effective apology;
      2. pay Mrs X a total of £1,000 to recognise the injustice caused to her and Y by the Council’s delays, poor communication and failure to secure Y’s special educational provision; and,
      3. reimburse Mrs X’s costs for one hour a week of special educational provision between February 2026 and June 2026, provided she can show it evidence of her costs.
  2. Within three months of our final decision, the Council will identify if it needs to make any changes to how it carries out reviews of EHC Plans. It should ensure that it can still meet the statutory deadlines to amend and issue plans, even if a parent or young person asks for EOTAS during the review. If it identifies any changes it will make, it will send us a time-bound action plan of when it will make these.
  3. The Council should provide us with evidence it has complied with the above actions.

Back to top

Decision

  1. I find fault causing injustice. The Council has agreed actions to remedy injustice.

Back to top

Investigator's decision on behalf of the Ombudsman

Print this page

LGO logogram

Review your privacy settings

Required cookies

These cookies enable the website to function properly. You can only disable these by changing your browser preferences, but this will affect how the website performs.

View required cookies

Analytical cookies

Google Analytics cookies help us improve the performance of the website by understanding how visitors use the site.
We recommend you set these 'ON'.

View analytical cookies

In using Google Analytics, we do not collect or store personal information that could identify you (for example your name or address). We do not allow Google to use or share our analytics data. Google has developed a tool to help you opt out of Google Analytics cookies.

Privacy settings