Summary: We will not investigate this complaint about a delay in the Council’s handling of the statutory children’s complaint process because the Council has agreed to progress the complaint under the statutory procedure promptly and consider an appropriate remedy for the delay. This provides a proportionate remedy for the injustice caused so we are satisfied with the actions the Council has agreed to take.

The complaint

  1. Mr Y complains the Council has failed to provide him or his advocate with the response to his complaint under Stage Two of the children’s statutory complaint process.
  2. Mr Y has been unable to get the response, albeit he is aware that the stage two process has been carried out, causing distress and uncertainty.

Back to top

The Ombudsman’s role and powers

  1. We investigate complaints about ‘maladministration’ and ‘service failure’. In this statement, I have used the word fault to refer to these. We provide a free service but must use public money carefully. We may decide not to start or continue with an investigation if we are satisfied with the actions an organisation has taken or proposes to take. (Local Government Act 1974, section 24A(7), as amended) 

Back to top

How I considered this complaint

  1. I considered information Mr Y and the Council provided and considered the Ombudsman’s Assessment Code.

Back to top

My assessment

  1. If we were to investigate it is likely we would find fault causing the complainant injustice because Mr Y’s advocate told the Council in writing he wanted to progress his complaint to Stage Two, which the Council acknowledged at the end of 2025. However, to date neither he, nor his advocate, have received a response. As the Council should have provided Mr Y with a response within 65 working days under the statutory process, which passed in March 2026, it has now failed to provide the response in the statutory time frame, causing delay. It is likely we would consider this fault.

Back to top

Agreed Action

  1. To its credit the Council has agreed to resolve the complaint. It has agreed to:
    • Complete the stage two response and provide it to Mr Y and his representative within one month of the final decision;
    • Inform Mr Y of his right to complain to the Ombudsman after completing stage three of the statutory complaint process;
    • Consider and provide an appropriate remedy for the delay at stage two of the statutory complaints procedure, we would suggest £50 per month of delay, once the stage three is concluded or when Mr Y confirms he does not wish to progress his complaint to stage three.
  2. The Council should provide us with evidence that the above recommendation has been completed. 

Back to top

Final decision

  1. We will not investigate Mr Y’s complaint because the Council has agreed to resolve the complaint early by providing a proportionate remedy for the injustice caused to Mr Y.

Back to top

Investigator's decision on behalf of the Ombudsman

Print this page

LGO logogram

Review your privacy settings

Required cookies

These cookies enable the website to function properly. You can only disable these by changing your browser preferences, but this will affect how the website performs.

View required cookies

Analytical cookies

Google Analytics cookies help us improve the performance of the website by understanding how visitors use the site.
We recommend you set these 'ON'.

View analytical cookies

In using Google Analytics, we do not collect or store personal information that could identify you (for example your name or address). We do not allow Google to use or share our analytics data. Google has developed a tool to help you opt out of Google Analytics cookies.

Privacy settings