Rother District Council (24 014 642)
Category : Planning > Planning applications
Decision : Closed after initial enquiries
Decision date : 27 Nov 2024
The Ombudsman's final decision:
Summary: We will not investigate this complaint about how the Council dealt with a planning application. This is because we are unlikely to find fault.
The complaint
- Mr X has complained about how the Council dealt with his neighbour’s planning application. Mr X says the development will have a significant impact on his property and the Council has failed to properly address the concerns he raised about the proposal.
The Ombudsman’s role and powers
- We investigate complaints about ‘maladministration’ and ‘service failure’, which we call ‘fault’. We must also consider whether any fault has had an adverse impact on the person making the complaint, which we call ‘injustice’. We provide a free service, but must use public money carefully. We do not start or continue an investigation if we decide there is not enough evidence of fault to justify investigating. (Local Government Act 1974, section 24A(6), as amended, section 34(B))
- We consider whether there was fault in the way an organisation made its decision. If there was no fault in how the organisation made its decision, we cannot question the outcome. (Local Government Act 1974, section 34(3), as amended)
How I considered this complaint
- I considered information provided by Mr X and the Council.
- I considered the Ombudsman’s Assessment Code.
My assessment
- When a local authority receives a planning application it must look at the development plan and material planning considerations to decide if the proposal is acceptable. Material considerations relate to the use and development of the land in the public interest and includes matters such as the impact on neighbouring properties and the relevant planning policies. It is for the decision maker to decide the weight to be given to any material considerations in determining a planning application.
- The Ombudsman does not act as an appeal body for planning decisions. Instead, we consider if there was any fault with how the decision was made.
- In this case, I am satisfied the Council properly assessed the acceptability of the development, including the impact on neighbouring properties, before granting planning permission. The case officer’s report referred to Mr X’s objections and addressed the concerns he raised. However, the officer decided the development would not unreasonably impact neighbouring properties. The Council also explained further in response to Mr X’s complaint why it did not consider there would be an unacceptable impact on his home.
- Mr X says the Council did not respond to the concerns he raised about the application. However, Mr X’s objections were addressed in the case officer’s report and the Council was not required to discuss these further with Mr X before it determined the application.
- Mr X believes building regulations are being breached and said the issues he raised about the boundary have not been considered. However, concerns about the safety of the development are not a material planning matter and building regulation approval is separate to planning permission. It is also not for the Council to get involved with boundary issues as this will be a private civil matter between Mr X and his neighbour.
- I understand Mr X disagrees with the Council’s decision to grant planning permission. But the Council was entitled to use its professional judgment to decide the application was acceptable and the Ombudsman cannot question this decision unless it was tainted by fault. As the Council properly considered the application, it is unlikely I could find fault.
Final decision
- We will not investigate Mr X’s complaint because we are unlikely to find fault by the Council.
Investigator's decision on behalf of the Ombudsman