Summary: We will not investigate this complaint about how the Council dealt with a planning application. This is because we are unlikely to find fault.
The complaint
- The complainant, whom I shall refer to as Mr X, has complained about how the Council dealt with his neighbour’s planning application. Mr X says the Council failed to properly consider his concerns about the development and the proposed extension will be oversized and cause a significant loss of light to his property.
The Ombudsman’s role and powers
- The Ombudsman investigates complaints about ‘maladministration’ and ‘service failure’, which we call ‘fault’. We must also consider whether any fault has had an adverse impact on the person making the complaint, which we call ‘injustice’. We provide a free service, but must use public money carefully. We do not start or may decide not to continue with an investigation if we decide there is not enough evidence of fault to justify investigating. (Local Government Act 1974, section 24A(6))
How I considered this complaint
- I considered information provided by Mr X and the Ombudsman’s Assessment Code.
My assessment
- When a local authority receives a planning application it must look at the development plan and material planning considerations to decide if the proposal is acceptable. Material considerations relate to the use and development of the land in the public interest and includes matters such as the impact on neighbouring properties and the relevant planning policies. It is for the decision maker to decide the weight to be given to any material considerations in determining a planning application.
- The Ombudsman does not act as an appeal body for planning decisions. Instead, we consider if there was any fault with how the decision was made.
- In this case, I am satisfied the Council properly assessed the acceptability of the development, including the impact on neighbouring properties, before granting planning permission. The case officer’s report referred to Mr X’s objections and addressed his concerns. However, the officer decided the extension would comply with the BRE light test and would not cause an unacceptable loss of light to Mr X’s home or affect amenity to such an extent it would warrant the refusal of the application.
- Mr X disagrees and says further analysis should have been carried out in relation to potential loss of light. But the case officer was entitled to use their professional judgment to decide the application was acceptable and the Ombudsman cannot question this decision unless it was tainted by fault. As the Council properly considered the application, it is unlikely I could find fault.
Final decision
- We will not investigate Mr X ’s complaint because we are unlikely to find fault by the Council.