North East Lincolnshire Council (24 001 091)
Category : Planning > Building control
Decision : Closed after initial enquiries
Decision date : 09 May 2024
The Ombudsman's final decision:
Summary: We will not investigate this complaint about how the Council dealt with a building control matter. This is because it is unlikely we could achieve a worthwhile outcome for the complainant.
The complaint
- Mr X used the Council’s building control service when he extended his property. Mr X says the Council did not properly inspect the building work before it issued a completion certificate and he has since discovered defects with the work.
The Ombudsman’s role and powers
- We investigate complaints about ‘maladministration’ and ‘service failure’, which we call ‘fault’. We must also consider whether any fault has had an adverse impact on the person making the complaint, which we call ‘injustice’. We provide a free service, but must use public money carefully. We do not start or continue an investigation if we decide:
- further investigation would not lead to a different outcome, or
- we cannot achieve the outcome someone wants, or
- there is no worthwhile outcome achievable by our investigation.
(Local Government Act 1974, section 24A(6), as amended, section 34(B))
How I considered this complaint
- I considered information provided by Mr X and the Ombudsman’s Assessment Code.
My assessment
- Most building work will require building regulation approval. The regulations will set the standards for design, construction and ensure the health and safety of the people living in or around the building.
- Mr X says the Council failed to properly inspect the building work before it issued the completion certificate. However, while the Council will normally visit the site at various stages of the build, it does not act as a clerk of works or a site manager and the responsibility for compliance with the regulations rests with the building owners and builders. The council’s role is to maintain the building standards for the public in general rather than protect the private interests of an individual.
- Mr X says he will incur significant costs repairing the defective work to make the building safe. However, caselaw has established that where a council has issued a completion certificate and the work is later found to be substandard, liability for any defects rests with those that commission the work and those that carry it out. We therefore cannot hold the Council responsible for substandard work by the builder and it is unlikely we could achieve a worthwhile outcome for Mr X by investigating his complaint.
Final decision
- We will not investigate Mr X’s complaint because it is unlikely an investigation would achieve a worthwhile outcome.
Investigator's decision on behalf of the Ombudsman